Bondada in Upper Circuit today
Share

Bondada Engineering shares hit a 5% upper circuit on June 24, 2025, after bagging a historic ₹836 crore order from Tamil Nadu Green Energy Corporation to develop India’s largest BESS project under the BOO model.

Bondada Engineering Share Price Hits Upper Circuit 

Bondada Engineering Limited shares price jumped by 5% and hit the upper circuit limit on June 24, 2025, following a major announcement. The company disclosed that it has received a Letter of Award (LOA) from Tamil Nadu Green Energy Corporation Limited (TNGECL) to establish one of the largest Battery Energy Storage Systems (BESS) in its history.

Below are the key highlights from the company’s official release to the stock exchange.

Landmark BESS Project Secured

Bondada Engineering Limited announced the receipt of an LOA from Tamil Nadu Green Energy Corporation Limited for the development of standalone grid-scale Battery Energy Storage Systems with a combined capacity of 400 MWh. The installations will be located at Vellalaviduthi and Thennampatty in Tamil Nadu.

This project represents the highest storage capacity order ever received by Bondada in its BESS segment, aligning with the company's vision to reach 10 GW capacity in the green energy space by 2030.

Project Model and Strategic Significance

The project will be developed under the Build-Own-Operate (BOO) model. Bondada Engineering emerged as the successful bidder through a tariff-based competitive bidding process conducted by TNGECL under the state component of Viability Gap Funding (VGF) support.

The order underscores Bondada's growing leadership in the energy storage sector and reaffirms its commitment to advancing India's clean energy ecosystem.

Key Project Details of ₹836 Order 

ParticularsDetails
Awarding EntityM/S Tamil Nadu Green Energy Corporation Limited
Capacity400 MWh (200 MW x 2 hours)
ModelBOO with two-cycle charging/discharging for "on-demand" usage
LocationsVellaviduthi and 400/230-110 KV Thennampatty substations
Execution Timeline18 months from execution of the Battery Energy Storage Purchase Agreement
Order Value₹8,36,00,64,000/- (inclusive of GST) over a 12-year period
Related Party InvolvementNone

Supporting National and State-Level Energy Goals

The BESS project supports both India’s National Framework for Energy Storage Systems (NFESS) 2023 and Tamil Nadu’s goal of achieving 50% renewable energy share by 2030. The system is expected to be fully integrated with the state electricity grid by 2027, contributing toward broader goal of achieving 500 GW non-fossil fuel capacity.